Gas line relocation/service work is moving along well. Xcel/NPL crews expect to have their work from 38th - 39th, and from 43rd - 44th, completed this Saturday, July 23rd. (Also, due to excellent cooperative work between the contractor/city team and Xcel, expedited potholing work by Xcel was completed in just half a day yesterday, allowing the road to be reopened sooner than expected.) As their work continues this week, we are placing electrical conduit along the west side. That work will be ongoing for the next few weeks.
Upon completion of the gas line work this Saturday, Concrete Works will immediately begin roadway preparation (on Monday, July 25th) for the paving of Tennyson from 43rd to 44th, which is scheduled for Thursday, July 28th or Friday, July 29th.
Also on Monday, July 25th, Xcel/NPL crews will begin their work on the gas line relocation from 41st to 43rd. We will also be working on irrigation sleeve placement at 43rd next week.
We are planning to begin trolly track removals from 38th - 39th on Tuesday, July 26th, and that will take us most of that week. Once those removals are complete, we will immediately begin roadway paving preparation work and we should be ready to pave that block near the end of the week of August 1st. New roadway concrete is coming soon!